Not many takers for rooftop solar installations despite subsidies

The scheme is aimed at promoting a greener and sustainable energy.

Visakhapatnam: Offtake under the Pradhan Mantri Suryaghar scheme of February 2024, under which householders can install solar power plants on their rooftops at subsidised cost, has been slow in certain regions of Andhra Pradesh, particularly Srikakulam and West Godavari circles.

The scheme is aimed at promoting a greener and sustainable energy. Customers using up to 120 units of electricity monthly can install a one-kilowatt solar power plant costing ₹60,000 with a subsidy of ₹30,000. Likewise, those consuming up to 240 units monthly can set up a two-kilowatt power plant costing ₹1.2 lakh with a subsidy of ₹60,000. Those utilising up to 360 units monthly can establish a three-kilowatt power plant costing ₹1.8 lakhs of which ₹78,000 will be the subsidy component.

Despite these initiatives, response rates have remained low, particularly from high-rise buildings, upscale neighbourhoods and gated communities. They are concerned about solar panels getting damaged during storms and other associated risks.

However, officials are continuing their efforts. They have reassured the public that the Pradhan Mantri Suryaghar scheme will remain in effect until March next year and residents can take advantage of the 50 per cent subsidy.

APEPDCL officials are actively contacting applicants, who have not completed all the necessary formalities for installing rooftop solar power plants. They are informing other consumers about the long-term benefits and cost savings associated with such plants.


----

Given here is the circle-wise status of applications as of February 23, 2025:

Srikakulam: Registrations 2,793; Formalities completed 710; Installations completed 1,480; Installations pending 207.

Parvathipuram Manyam: Registrations 556; Formalities completed 90; Installations completed 143; Installations pending 40.

Vizianagaram: Registrations 7,753; Formalities completed 623; Installations completed 472; Installations pending 119.

Visakhapatnam: Registrations 6,468; Formalities completed 1,365; Installations completed 1,143; Installations pending 119.

Anakapalle: Registrations 1,931; Formalities completed 648; Installations completed 456; Installations pending 177.

Alluri Seetharama Raju: Registrations 1,931; Formalities completed 16; Installations completed 4; Installations pending 11.

Kakinada: Registrations 4,628; Formalities completed 866; Installations completed 707; Installations pending 147.

Dr. B.R. Ambedkar Konaseema: Registrations 4,085; Formalities completed 372; Installations completed 274; Installations pending 85.

East Godavari: Registrations 9,384; Formalities completed 1,018; Installations completed 790; Installations pending 210.

Eluru: Registrations 14,526; Formalities completed 2,382; Installations completed 796; Installations pending 1,556.

West Godavari: Registrations 13,599; Formalities completed 1,018; Installations completed 790; Installations pending 210.


( Source : Deccan Chronicle )