Jawaharnagar dumping yard to be capped by February

Corporation officials said the work would be completed by February.

Hyderabad: The GHMC has completed capping 75 per cent of the Jawaharnagar dumping yard.

Corporation officials said the work would be completed by February. The GHMC has capped 3.4 lakh square metres out of the total spread of 4.44 lakh sq.m. The capping will be taken up in six phases. The first phase of capping will be completed by June 30.