Top

Telangana CM rejigs Bhagiratha timeline, P-1 by December

Chief Minister K. Chandrasekhar Rao cautioned officials that there would be problems when supply began.

Hyderabad: Chief Minister K. Chandrashekhar Rao on Saturday asked officials to divide Mission Bhagiratha works into two parts and complete the first segment by December 31 and the second by June 2018.

He cautioned officials that there could be teething troubles like leakage from and breakage of pipes due to water pressure and problems with valves when supply begins, and they must be attended to immediately. He said when the programme was implemented in Gajwel, small problems persisted for a couple of months.

Mr Chandrasekhar Rao said that under Part-I, 25,000 habitations should get purified water by December end as a New Year gift. Under Part-II all internal works should be done to fix taps in every household.

Officials told Mr Rao that drinking water was being supplied to 3,431 villages of the targeted 24,225, another 5,443 villages would be covered by October end, 6,006 by November-end and 9,345 villages by December-end.

Mr Chandrasekhar Rao praised the electricity department for making arrangements to supply the required power for Mission Bhagiratha.

TS Genco and Transco chairman and managing director D. Prabhakar Rao informed the Chief Minister that all electrical works on Mission Bhagiratha would be completed by October 2.

Mr Prabhakar Rao said the work such as construction of sub-stations, arranging power cables and installing transformers were completed at a cost of Rs 300 crore.

He said to supply 221 MW uninterrupted power to Mission Bhagiratha, 42 sub stations, 1,190-km of cables and 87 power transformers were put in place.

( Source : Deccan Chronicle. )