Land Acquisition Begins for RRR South Corridor
2,885 Acres to Be Acquired Across 49 Villages in Vikarabad and Rangareddy; Officials Set March 2027 Deadline
The Telangana government has issued land acquisition notifications for the construction of the southern segment of the Regional Ring Road (RRR) in Vikarabad and Rangareddy districts, with about 1,016 acres proposed to be acquired in Vikarabad and another 1,869 acres in Rangareddy.
With this, the Vikarabad district administration has initiated the process of acquiring land across 21 villages in four mandals. Vikarabad district collector Deepak Tiwari has issued orders appointing the Vikarabad revenue divisional officer (RDO) as the land acquisition officer and the additional collector (Revenue) as the project administrator.
This is the first appointment of district-level land acquisition officials for the RRR South corridor and follows the submission of land acquisition proposals by the Hyderabad Metropolitan Development Authority (HMDA). The Joint Metropolitan commissioner and estate officer submitted the required documents to the District Collector, following which the district administration initiated the process of appointing the officials.
The acquisition will be undertaken under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, along with the Telangana Amendment Act. The collector's orders also mention an exemption granted by the government from the provisions of Chapters II and III of the legislation, potentially enabling the acquisition to proceed without the usual Social Impact Assessment and Expert Group appraisal.
The 21 villages identified for acquisition in Vikarabad district are spread across Mominpet, Nawabpet, Pudur and Vikarabad mandals.
In Rangareddy district, officials have initiated the land acquisition process in 28 villages spread across the Shadnagar, Kandukur and Ibrahimpatnam revenue divisions. A total of 1,869 acres will be acquired for the construction of a 75.67-km stretch of the RRR South corridor. A preliminary land acquisition notification has been issued, following which officials will verify land details, ownership rights, survey numbers and the extent of land.
Officials will first identify government lands and acquire private patta lands wherever necessary. The Rangareddy district administration has decided to complete the acquisition process in three stages. In the first stage, gram sabhas will be conducted to receive objections and suggestions from farmers and landowners. The objections will be examined in the second stage and necessary changes made, followed by surveys and verification of ownership details. In the third stage, compensation will be determined and paid to eligible landowners.
The district revenue administration has set a target of completing the land acquisition process by March 2027. While the acquisition is under way, HMDA officials will prepare the final Detailed Project Report (DPR) for the project, allowing land acquisition and technical planning to proceed simultaneously.
Two greenfield radial roads are also proposed to be developed in connection with the RRR South corridor. One will connect Kongarakalan and Amangal over a distance of 42 km and is proposed to be named the Ratan Tata Greenfield Radial Road, while the other will connect Budvel and Kodangal over 81 km.
Once completed, the radial roads are expected to improve connectivity between the Outer Ring Road (ORR), Bharat Future City, Rajiv Gandhi International Airport at Shamshabad and southern Telangana districts. The RRR South project is expected to play a key role in the development of areas surrounding Hyderabad by improving connectivity to industries, logistics hubs and emerging urban centres while reducing travel time.