Amaravati: Chief Minister N Chandrababu Naidu directed the officials to get prepared to meet the increasing Electricity demand which is expected to reach 14,852 MW over the next six months.
Power demand increased by 18.23 per cent between April and November compared to the corresponding period last year.
Officials attributed the unexpected surge in electricity demand to the impact of El Niño.
The Chief Minister reviewed the progress of the Energy department at his camp office today. Several issues of power sector including Investments in the energy sector and the progress of new projects, impact of El Niño on electricity consumption and the resulting increase in power demand, along with the demand-supply situation, Green Energy Corridor-III, pumped storage projects and the establishment of electric vehicle (EV) charging stations were discussed. The discussions also centred round Investments secured in the energy sector at the CII Partnership Summit in Visakhapatnam and measures to fast-track the implementation of the projects.
Officials said under Green Energy Corridor-III, plans are being prepared to develop a major power transmission network in Andhra Pradesh at an estimated cost of Rs 21,838 crore.
The Green Energy Corridor will facilitate the transmission of 47 GW of renewable energy.
Pumped storage projects with a total proposed capacity of 36,050 MW are being planned across the State.
As many as 27 potential locations for pumped storage projects have been identified in the Polavaram region, with a target to generate 36,050 MW of power.
Since June 2024, approvals have been granted for 103 projects in the energy sector, involving investments of Rs 4.20 lakh crore.
Investment agreements worth ₹2.56 lakh crore were signed in the energy sector during the CII Partnership Summit held in Visakhapatnam.
Rooftop solar systems are being planned for government welfare schools and hostels, with 2,962 educational institutions proposed to be brought under solar power coverage. Andhra Pradesh ranks fourth in the country in the implementation of the PM Surya Ghar scheme. More than 7.42 lakh rooftop solar installations have been completed so far. The State aims to provide 9 lakh PM Surya Ghar connections by the end of this month.
Progress is being made on solar power plants with a combined capacity of 1,162 MW at 224 locations under the PM-KUSUM scheme.
Land acquisition for PM-KUSUM projects has been completed 100 per cent, while civil works have achieved 91 per cent progress, the officials informed the Chief Minister.