Grid Bottlenecks Force India To Curb 8,133 GWh of Solar Power In April-June Quarter

New clean energy plants coming into operation ahead of schedule and delayed transmission projects force solar power ​output curtailments.

By :  Reuters
Update: 2026-07-28 13:09 GMT
(File Image)

New Delhi: India held back 8,133 gigawatt hours (GWh) of solar power for the April-June ​period as the grid struggled to ‌absorb renewable electricity owing to transmission bottlenecks and grid security requirements, the government said on Tuesday.

Solar power ​curtailment stood at 2,417 GWh in April, ​rose to 3,235 GWh in May and ⁠was 2,481 GWh in June, the minister ​for renewable energy, Yesso Naik, said in a ​written statement.

New clean energy plants coming into operation ahead of schedule and delayed transmission projects force these power ​output curtailments.

The government said curtailment and restrictions ​on solar generation were being carried out to maintain ‌grid ⁠security and because of a mismatch between the commissioning of transmission lines and renewable energy projects.

The disclosure highlights a growing challenge for India ​as it ​expands renewable ⁠energy capacity to meet its clean energy targets of 500 GW ​by 2030 from the present 288 GW.

Responding ​to ⁠a question on whether renewable energy curtailment had emerged as a challenge for the country's ⁠clean ​energy transition, the government said ​curtailment is implemented to ensure reliable and secure operation of ​the grid.