Flyover lacks speedy makeover
TN Highways Department to construct road over-bridge to ease traffic chaos in North Chennai.
Chennai: To ease the traffic chaos in North Chennai, the state Highways Department has taken up construction of a road over-bridge at VyasÂarÂpadi and a flyover at MoÂolÂakadai junction on arterial Grand Northern TrÂuÂnk (GNT) Road three years ago. But, much to the dismay of motorists, the work is progressing at a snail’s pace.
Work on the construction of the Rs 49.55 crore flyover at Moolakadai junÂction on GNT road was initially hit due to delays in land acquisition and shifting of water pipeÂliÂnes. “We have cleared all the hurdles and handed over the area required for construction of the flyover to the contractor. But the financial problems faced by the contractor has resÂulted in slow progress of work,” sources in the higÂhways department said.
The official said that they had issued notice to the contractor for delay in construction work. “We will impose heavy penalty on the contractor for the delay,” the official said, pointing out that so far only 40 per cent of the total work has been completed even though the construction of the four-lane flyover began in February 2011. “We have fixed a new deadline of September 2014 for the contractor to complete the work,” the official said.
As for as the delay in laying the service roads is coÂnÂcerned, sources said thÂat MaÂdhavaram side of the seÂrvice road would be coÂmÂpleted by next month end while the Perambur siÂde road would laid by JaÂnuary 2014. The flyover at the GNT Road and MaÂdhÂaÂvÂaram High Road inÂtÂerÂsÂeÂction would smÂoÂoÂtÂhÂen flow of traffic in the area, as it witnesses heavy movement of traffic, particularly lorries and containers.
The work on the Rs 80.68 crore Vyasarpadi road ovÂer bÂridge to replace existing vehicular subway beÂgÂan in 2010 under the higÂhÂwÂaÂys department and SouÂtÂhern Railway, and was aimed at facilitating the smooth flow of vehicles on GNT Road. The Y shaped RoB takes off on Basin BrÂidge Road and one of the arms lands at GNT road and the other at SathÂyaÂmÂuÂrthy Nagar main road. “The delay in shifting of drinking water pipeline has resulted in works delay,” a senior highways department official said.
K. Subramani, a resident of Red Hills, said that GNT road is an arterial road connecting Chennai with Kolkata via Andhra PraÂdesh and Odhisha. “The road is not free even during night hours as movement of trucks and containers towards and from Chennai Port is heavy. The completion of the bridge and flyover works will ease traffic on this busy road,” he said.
( Source : dc )